Factory Drywalling
CPT contacted us to assist with factory drywalling and installation at CPT in Isando as part of their project for two new printing rooms.
They already had a clear picture in mind of what they required but also required two roller doors and one extra height double door installed and painting done.
Re-enforcement had to be build into the factory drywalling of the two rooms to allow for structural strength for the two roller doors to be installed. The opening of the walls where the rollers doors was fitted was trimmed with aluminium.
After all was completed 75mm aluminium skirting was fitted .
The factory drywalling was then painted one coat plaster primer and two coats low sheen white paint. As can be seen the final product was not only functional but also aesthetically pleasing and met the desired outcome of client.
The structure of the partitioning was created from galvanized floor track which was fixed to the floor with nail in screws, aluminium natural anodized wall channel fitted to the ceilings and factory drywalling where required and galvanized studs as per supplier recommendation. Corner sections done with galvanized angle and all secured with drywall screws.
It needs to be noted that accuracy when constructing the factory drywalling is of utmost importance. If the structure is poorly constructed the end product will be of poor visual quality.After the drywalling structure was completed 12.5mm Gypsum board cladding was used.
The extra height double doors fitted had natural anodized aluminium frames, natural anodized hinges, medium duty hollow core doors and standard lock sets with dead bolts.
Joint was then fiber taped and two coats Rhinoglide applied. Once dry, the joints was sanded to a smooth finish in preparation of painting of the factory drywalling.
Well done to the team!!!